Client: Wetherby Racecourse
Location: Wetherby
Date of Possession: October 2016
Contract Type: Purchase
Wetherby Racecourse wanted a new building quickly for press & commentary from an ideal vantage point i.e. as high as possible!
As part of the design for a new stand at the course they contracted Britcab to supply & install a two storey modular building during the construction phase of the stand. We installed the building directly onto the steel framework of the stand and completed the building safely at great height with all logistics and site conditions taken into account. The new building was then used for a key race meeting in October 2016 prior to completion of the new stand. The building was then clad externally to match the new stand with the finished building blending in to the completed stand construction.
The client was more than happy with the design & communication throughout the process from enquiry to completion.